Do I Need a Building Permit for a Shed in Victoria?

When a freestanding shed is exempt under Schedule 3, and when you need a building permit before you build.


One of the most common questions we hear as building surveyors in North East Victoria is: do I need a building permit for a shed? In Victoria, the answer turns on Schedule 3 of the Building Regulations 2018, made under the Building Act 1993. Many freestanding sheds need a permit. A defined group of small freestanding Class 10a sheds does not.

The Schedule 3 exemption

Under Schedule 3, item 1 of the Building Regulations 2018, construction of a freestanding Class 10a building (a typical freestanding shed, garage or carport) is exempt from a building permit if all of the following apply:

  • Floor area not exceeding 10 m²
  • Height not more than 3 m, or not more than 2.4 m if the shed is situated within 1 m of a boundary
  • If it is appurtenant to another class of building on the same allotment (for example a house), it is located no further forward on the allotment than the front wall of that building
  • If it is the only Class 10a building and is not appurtenant to another class of building on the allotment, it is set back at least 9 m from the front street alignment and at least 2 m from each side street alignment
  • It is not constructed of masonry

Even when a building permit is not required, the shed must still comply with the National Construction Code where the Regulations apply. Schedule 3 exemptions are about the permit trigger, not a free pass on every other duty.

When you still need a building permit

If any Schedule 3 item 1 criterion is not met (for example the shed is larger than 10 m², taller than the height limits, masonry, or further forward than the front wall of the house), you need a building permit before you build. Attaching a shed to a dwelling, replacing a small shed with a larger one, or building where bushfire, flood or other site conditions drive engineered design, are all reasons to lodge early with a registered building surveyor.

Title covenants and owners corporation rules sit outside Schedule 3. They can restrict what you may build on the land, but they are not part of the Schedule 3 exemption test. Deal with them separately from the building-permit question.

What we need to assess a shed permit

  • Site plan showing setbacks and existing buildings
  • Manufacturer drawings or structural engineering for the shed
  • Allotment details and any easements or overlays you know about
  • Owner and builder (or owner-builder) details

Complete Form 1 and send it with your drawings via our contact form, or start from Forms & Downloads. When the design complies, we issue a building permit and list the mandatory notification stages that apply.

North East Victoria examples

We regularly assess shed and farm-building permits around Euroa, Shepparton, Benalla and Wangaratta. Soil conditions, wind region and bushfire attack level can change the engineering you need. Local knowledge helps keep lodgement complete the first time.

This guide covers Victorian law only. For Albury NSW and twin-city projects, see building permits Albury.

Started without a permit?

If the shed is already up, read our page on unauthorised building works and contact us early. Council may issue a building notice or building order. NEBA can advise on retrospective approval pathways where they remain available. Options narrow if you keep building after a notice or order.

Contact NEBA with shed size, height and a rough site sketch for a clear assessment and fee estimate.